SINOPEC
RegulationsforProductionPreparationandTrialrunofConstructionProjects
April1998
NoticeonPrintingandIssuingtheSINOPECRegulationsforProductionPreparationandTrialrunofConstructionProjects
AllcompaniesdirectlyunderSINOPEC,headfactory,factoriesandinstitutes,
TheSINOPECRegulationsforProductionPreparationandTrialrunofConstructionProjectsisnowprintedandissuedtoyou,whichshallbeimplementedseriously.AnyprobleminimplementationshallbefedbacktotheSINOPECEngineeringDepartment.
TheoriginalSINOPECRulesfortheWorkofProductionPreparationandTrialrunofPetrochemicalConstructionProjects(fortrail)(ZhongShiHua[1990]JianZhiNo.34)shallbeabolishedatsametime.
SINOPEC
April20,1998
Chapter1General
Article1Tointensifytheproductionpreparationworkofpetrochemicalconstructionprojectsandtosecurethesuccessoftrialrunwithmaterialatonetimeandtorealizeof“safe,stable,longtime,atfullcapacityandinbestquality”runningaftertrialrunwithmaterialsoastoobtainthereturnsofinvestment,thisregulationisworkedout.
Article2Thisregulationappliestoallnewlybuilt,expandedandtechnicalreformedlargeormediumsizedpetrochemicalconstructionprojectsoftheenterprisesdirectlyundertheChinaPetrochemicalCorporation(hereinafterreferredtoasSINOPEC).Itmayalsobeasreferencetootherconstructionprojects.
Article3Thelaborsafety,environmentprotection,firefightingandindustrialhealthinvolvedinthisregulationshallimplementrelevantlaws,codes,standardsandspecificationofSINOPECinforce.
Article4Theworkofproductionpreparationrunsthroughthewholeprocessoftheconstructionproject.Uponthereplyoftheapprovalofthefeasibilitystudy,theWorkingProgramofProductionPreparationshallbeworkedoutsoastobringtheworkofproductionpreparationandtrialrunwithmaterialintolinewithoverallcontrolplanoftheconstructionproject.
Article5Theworkofthetrialrunshallfollowtheprincipleof“thesingletrialrunshallbedoneearlier,thepurgingandairtightshallbestrict,thecombinedtrialrunshallbecomplete,thetrialrunwithmaterialshallbestableandtheeconomicreturnsshallbegood”soastobesafeandstableandtobesuccessfulatonetime.
Chapter2ProductionPreparation
Article6Thetasksofproductionpreparationare:
1.Organizationpreparation;
2.Personnelpreparation;
3.Technicalpreparation;
4.Materialpreparation;
5.Capitalpreparation;
6.Marketingpreparation;
7.Preparationofexternalconditions;
Article7OrganizationPreparation;
1.Uponthereplyoftheapprovalofthefeasibilitystudyoftheconstructionproject,theownershallorganizeproductionpreparationorganandbasedontheprogressoftheproject,theorganshallbeimprovedgraduallyaccordingtotheprincipleofsimplifiedandunifiedwitheffectivefunction,whichshallberesponsiblefortheworkoftheproductionpreparation.
2.Basedontherequirementsofoveralltrialrunsolutions,theownershallestablishaleadingorganforthetrialruntimelytoleadanddirectrelevantunitsinaunifiedwaytodotheworkwellofthesingletrialrun,thecombinedtrialrun,thetrialrunwithmaterialandtheproductiontest.
3.Basedonthedesignrequirementsandtheprogressoftheconstructionoftheprojectandcarryingouttheprincipleof“newsystemandnewmechanismfornewfactory”,theownershalltimelyorganizeproductionmanagementorgansatdifferentlevelssoastomeetactualneedofproductionmanagement.
Article8PersonnelPreparation
1.Theownershall,basedontheapprovedcriteriaforpersonnel,workoutoverallplanandannualplanforpersonneltoenterthefactoryandpersonsshallbeassignedtimely;
2.Fortheallocationofpersonnel,attentionshallbepaidtotheagestructure,culturalstratumandtechnicalclass.Personnelonceworkedonsameorsimilarpostsshallmakeup1/3oftotalnumberofpersonsoftheunit.Newemployeesshallberemovedfromoldenterpriseinacompleteestablishmentwayandrecruitedfromgraduatesofcollegesorpolytechnicschools,whoshallbetrained,testedandhealthcheckedandgoodonesshallbeemployed.
Thepersonnelforproductionmanagement,technicalpersonnelandmainoperators,analyzersandmaintenancepersonnelshallenterthefactory1or2yearspriortothetrialrunwithmaterial;
Theotherpersonnelshallenterthefactoryhalfayearofoneyearpriortothetrialrunwithmaterial.
3.Basedonthecharacteristicsofpetrochemicalandtherequirementofthetrialrunwithmaterial,theownershallworkoutatrainingplanforallpersonnelandtheworkoftrainingshallbegraspedseriouslysoastomakethestaff,techniciansandworkersatdifferentlevels,afterrigidtrainingandtesting,beinconformitywithconditionstoworkontheirposts.
(1)Thetrainingofthestaffshallbestressedontheirprofessionsandrelevantknowledgeeducationsoastoraisetheirmanagementleveltomeetrequirementsoftrialrundirectionandproductionmanagement;
(2)Thetrainingofthebackbonesoftechnicians,teamleadersandshiftleadersandkeyoperatorsshallbestressedonthestudyofprofessionalknowledge,thepracticeinunitsofsamekind,computersimulationandtrainingonknowledgeoflaborsafety,environmentprotection,firefightingandindustrialsanitarytoraisetheirbusinessqualityandtechnicallevelviathesingletrialrunandthecombinedtrialrunastomakethembeproductionandtechnicalbackbonesinthetrialrunwithmaterial;
(3)Thenewworkersshall,after3-classsafetyeducationonentrythefactory,betrainedforthewholeprocessinfollowing5stages:
basicknowledgeandprofessionalknowledgeeducation;
practiceinunitsofsamekind;
practiceinpost;
trainingofcomputersimulationandparticipationoftrialrunbeforethetrialrunwithmaterial.Throughtraining,makethembefamiliarwithprocessflowandgraspkeypointsofoperationtobecome“3-understandsand6-cans”(3-understands:
understandprinciple,understandstructure,understandsolutionandspecifications;
6-cans:
canreaddrawings,canoperate,canmaintain,canliaison,canhandletrouble)andtheir“6-abilities”raised(thinkingability,operationability,workingability,coordinationandorganizingability,counteraccidentability,selfprotectionandrescuingability,selfrestrainingability).
Oncompletionofthetrainingofeachstage,rigidtestshallbemade.Themarksofthetestshallbeputintopersonaltechnicalfiletobeasthebaseforthecertificateofworkingonthepost.
4.Thepracticeintheunitofsamekindshallbeorganizedbytheownerinacompleteestablishmentwaytocarryout“6-fixings”(fixingtask,fixingtime,fixingpost,fixingpersonnel,fixingpracticeteamleader,fixingperiodictesting)andsingthecontractof“2-contracts-1-replacing”withtrainerunit(contractedteachingbytrainerunit,contractedabletobytrainerunit,replacingtheworkofthepostunderthesupervisionofthetrainingmaster);
5.Forimportedunits,accordingtowhatspecifiedinthecontractandtheactualneedofthetrialrun,thekeen-wittedandcapableproductionbackbonesshallbeselectedfromdepartmentstobetechnicallytrainedabroad.ThenamelistoftraineesabroadandtheplanoftrainingshallbereportedtoSINOPECEngineeringDepartmentandotherrelevantdepartmentsforexaminingandapproval.Aftertrainingabroadandcomingbacktothefactory,theyshallplaytheroleofbackboneinproductionpreparationandtrialrunwithmaterial.Thetraineesabroadshallserveintheunitnotlessthan3yearsafterthetrialrunwithmaterialtomakedeservedcontributionstothesafeandstablerunningoftheunitandthemeetingofthestandardoftheunit.
6.Inthetrainingofallpersonnel,theworkofcultivationofideology,styleanddisciplineandprofessionalmoraleducationshallbegraspedwell.Differenteffectivewaysshallbetakentopromoteselfeducationandselfraisingoftheemployeestostimulatethespiritof“loveChina,vitalizeSINOPEC”andtoinheritanddevelopfinetraditionofpetrochemicalsystemandtodotrooptrainingofideologyandstyle,intensifymanagement,setrigidrequirementsoastocultivateateamofemployeeswhohaveideal,cultureanddiscipline,
Article9TechnicalPreparation
1.Themaintasksofthetechnicalpreparationaretoworkoutdifferenttrialrunsolutions,productiontechnicaldocumentsandmanagementregulationssoastomakeproductionpersonnelgrasptechnologyofdifferentunits.
2.Theownershallestablishmanagementsystemofproductiontechnologyasearlyaspossible.Theproductionmanagementcardersandtechnicians,throughdifferenttechnicalpreparationworkofparticipatingtechnicalnegotiationanddiscussionofdesignsolutionsandreviewingofdesign,shallskillfullygraspthetechnologiesoftheprocess,equipment,instruments(includingcomputers),safetyandenvironmentprotectionandbecapabletohandledifferenttechnicalproblemsindependently.
3.Theownershall,basedonthedesignrequirementsandtheOutlinesofProductionPreparationWork,workoutoveralltrialrunsolutiononeyearpriortothetrialrunwithmaterial,whichshallberepeatedlymodified,deepenedandoptimized.
4.FortheoutlineforformulationoftheOutlineofProductionPreparationWork,seeAppendix1.
5.Fortheout