临电施工组织设计16.docx
- 文档编号:6204822
- 上传时间:2023-05-09
- 格式:DOCX
- 页数:134
- 大小:726.46KB
临电施工组织设计16.docx
《临电施工组织设计16.docx》由会员分享,可在线阅读,更多相关《临电施工组织设计16.docx(134页珍藏版)》请在冰点文库上搜索。
临电施工组织设计16
温州市鹿城区中央涂A-2安置房地块建设工程
临
时
用
电
施
工
组
织
设
计
编制人:
审批人:
编制日期:
一、编制依据··················································3
二、电工及用电人员············································3
三、负荷计算··················································4
四、电源······················································8
五、配电系统··················································9
六、配电线路及用电计算········································9
七、配电箱··················································102
八、接地、接零··············································102
九、照明····················································103
十、施工用电管理············································105
十一、安全用电技术措施······································103
十二、触电的急救措施········································105
十三、安全措施·····························...·······.····106
十四、附平面图、各种电箱系统图·······························117
温州市鹿城区中央涂A-2安置地块建设工程
临时用电施工组织设计
一、编制依据:
1)、《施工现场临时用电安全技术规范》(JGJ46-2005);
2)、建设工程施工现场供用电安全规范(GB50194-2011);
3)、温州市《建设工程施工现场临时用电安全技术指南》;
4)、温州市《安全文明施工设施标准化图例》;
5)、《施工用电检查评分表》(JGJ59-2011);
6)、本工程施工组织设计
二、工程概况
建设单位:
温州市鹿城区改建工程指挥部
BT单位:
温州海嘉建设有限公司
设计单位:
浙江同方建筑设计有限公司
监理单位:
大连泛华建筑工程监理有限公司
总承包单位:
深圳中海建筑有限公司
建设地点:
温州市鹿城区昆仑路与瓯南路交叉口
项目概况:
温州市鹿城区中央涂A-2安置房,位于温州市鹿城区江滨西路A线南侧,面临瓯江,东侧为规划瓯南路,南侧为规划昆仑路及民宅,西侧为已建2层厂房及牛三角路。
工程总建筑面积218501㎡(地上167950㎡,地下50851㎡)。
其地下2层,塔楼楼高均为96.50m。
合同工期1028天。
本工程设计使用年限50年,抗震设防烈度7度,建筑耐火等级一级,建筑类别一类,地下室、屋面防水等级二级。
±0.000相对的绝对高程为5.20(黄海高程)。
1#、2#楼用一台325KWA变压器,设置一个总配电箱,四个二级箱。
4#楼、6#楼及西边职工生活区用一台400KWA变压器,设五个二级箱。
3#、5#、7#楼合用一台400KWA变压器,设五个二级箱。
办公区、职工大生活区从东北边400KWA变压器的总配电室分别引三根电缆到办公区、生活区的三个二级箱。
钢筋加工场及木工加工场开关箱的设置:
1#、2#楼及其地下室设置一个加工场;4#、6#楼及地下室设置一个加工场;3#楼、5#楼、7#楼及其地下室设置一个加工场。
每栋楼设置一个楼层二级箱。
7栋楼的7台塔吊、7台施工升降机各设置一个开关箱。
木工加工机械、钢筋加工机械每台机械设置一个开关箱。
三、负荷计算
1#、2#楼用电统计表:
4#、6#楼及西侧生活区用电统计表:
3#、5#、7#楼用电统计表:
办公区、生活区用电统计表;
2、用电负荷复核:
根据恒智天成安全软件的计算,1#、2#楼用电总功率379KVA,选择SL7-315/10型三相电力变压器可满足使用要求,目前业主提供的SL7-315/10型三相电力变压器;4#、6#楼用电总功率419.4KVA,选择SL7-315/10型三相电力变压器可满足使用要求,目前业主提供的SL7-400/10型三相电力变压器;3#、5#、7#楼用电总功率477.2KVA,选择SL7-400/10型三相电力变压器可满足使用要求,目前业主提供的SL7-400/10变压器型三相电力变压器;办公区、大生活区用电总功率242.2KVA,选择SL7-160/10型三相电力变压器可满足使用要求,目前业主提供的SL7-400/10型三相电力变压器。
其高压侧电压为10kV同施工现场外的高压架空线路的电压级别一致。
综上所述,目前业主提供的4台变压器均能满足施工现场临时用电要求。
四、电源
现场临电用电电源由业主提供,有三台4000KVA、一台325KVA变压器供给,根据现场临建布置、临电设施的配备和总电源的提供情况,从总电源总配电箱处接至各个二级配电箱,然后从二级配电箱的600A空开各引出多路干线电缆至二级箱供塔吊、加工场、楼层、生活区、办公区施工使用。
二级配电箱置于塔吊下标准节旁和加工场旁。
电路布置线路及二级分配电箱位置见施工现场临电平面布置图。
五、配电系统
根据现场业主提供的现有变压器位置及容量,现场靠近电源位置一级配电箱供施工现场二级配电箱及照明开关箱用电。
施工现场的重要负荷(如塔吊)开关箱直接从二级电箱接驳电源,其他一般负荷电源从二级电箱及开关箱接驳(注:
分配电箱及开关箱由分包负责安装),现场配电采用“三级配电、二级保护”。
本临时配电采用TN-S系统,并按照“三级配电、两级保护”的原则安装各级配电箱,各级配电箱内漏电开关漏电动作电流及动作时间按照由大到小分级配置。
末端设备漏电开关按照设备负荷电流需要匹配设置,漏电动作电流不大于30mA,漏电动作时间为0.1S。
各级配电箱的具体配置详见系统图。
六、配电线路
1、 敷设方式:
本工程临时施工线路全部采用电缆敷设,动力电缆及三项负荷采用三相五线制电缆,单相负荷采用三芯电缆。
电缆穿过道路段或施工现场采用穿钢管保护埋地敷设,其他部位的电缆根据现场情况沿墙敷设。
2、 线径选择:
为了满足功能上的要求和安全因素,该项目施工配电电缆选用VV系列电力电缆,电力电缆的设置不小于计算结果数据。
1#、2#楼从变压器输出总干线采用VV4*185+1*75电缆,4#、6#楼干线采用VV4*240+1*120电缆,3#、5#、7#楼干线采用VV4*240+1*120电缆,办公区、生活区干线采用VV4*95+1*50电缆.。
3、主线路导线截面选择见临电干线总平面图
6.1、1#楼、2#楼用电计算
1、现场勘探及初步设计:
(1)本工程所在施工现场范围内无各种埋地管线。
(2)现场采用380V低压供电,设一配电总箱,内有计量设备,采用TN-S系统供电。
(3)根据施工现场用电设备布置情况,采用导线穿钢管埋地敷设,布置位置及线路走向参见临时配电系统图及现场平面图,采用三级配电,两极防护。
(4)按照《JGJ46-2005》规定制定施工组织设计,接地电阻R≤4Ω。
2、确定用电负荷:
(1)插入式振动器
Kx=0.3,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.3×1.1=0.33kW
Qjs=Pjs×tgφ=0.33×1.02=0.337kvar
(2)高压汞灯
Kx=0.6,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.6×1=0.6kW
Qjs=Pjs×tgφ=0.6×1.02=0.612kvar
(3)塔式起重机
Kx=0.85,Cosφ=0.6,tgφ=1.333
Pjs=Kx×Pe=0.85×55.5=47.175kW
Qjs=Pjs×tgφ=47.175×1.333=62.884kvar
(4)平板式振动器
Kx=0.3,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.3×1.1=0.33kW
Qjs=Pjs×tgφ=0.33×1.02=0.337kvar
(5)插入式振动器
Kx=0.3,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.3×1.1=0.33kW
Qjs=Pjs×tgφ=0.33×1.02=0.337kvar
(6)交流电焊机
Kx=0.5,Cosφ=0.4,tgφ=2.291
Pjs=Kx×Pe=0.5×23.4=11.7kW
Qjs=Pjs×tgφ=11.7×2.291=26.805kvar
(7)交流电焊机
Kx=0.5,Cosφ=0.4,tgφ=2.291
Pjs=Kx×Pe=0.5×23.4=11.7kW
Qjs=Pjs×tgφ=11.7×2.291=26.805kvar
(8)交流电焊机
Kx=0.5,Cosφ=0.4,tgφ=2.291
Pjs=Kx×Pe=0.5×23.4=11.7kW
Qjs=Pjs×tgφ=11.7×2.291=26.805kvar
(9)100m高扬程水泵
Kx=0.75,Cosφ=0.8,tgφ=0.75
Pjs=Kx×Pe=0.75×20=15kW
Qjs=Pjs×tgφ=15×0.75=11.25kvar
(10)建筑施工外用电梯
Kx=0.85,Cosφ=0.6,tgφ=1.333
Pjs=Kx×Pe=0.85×22=18.7kW
Qjs=Pjs×tgφ=18.7×1.333=24.927kvar
(11)高压汞灯
Kx=0.6,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.6×1=0.6kW
Qjs=Pjs×tgφ=0.6×1.02=0.612kvar
(12)交流电焊机
Kx=0.5,Cosφ=0.4,tgφ=2.291
Pjs=Kx×Pe=0.5×23.4=11.7kW
Qjs=Pjs×tgφ=11.7×2.291=26.805kvar
(13)100m高扬程水泵
Kx=0.75,Cosφ=0.8,tgφ=0.75
Pjs=Kx×Pe=0.75×20=15kW
Qjs=Pjs×tgφ=15×0.75=11.25kvar
(14)建筑施工外用电梯
Kx=0.85,Cosφ=0.6,tgφ=1.333
Pjs=Kx×Pe=0.85×22=18.7kW
Qjs=Pjs×tgφ=18.7×1.333=24.927kvar
(15)塔式起重机
Kx=0.85,Cosφ=0.6,tgφ=1.333
Pjs=Kx×Pe=0.85×55.5=47.175kW
Qjs=Pjs×tgφ=47.175×1.333=62.884kvar
(16)插入式振动器
Kx=0.3,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.3×1.1=0.33kW
Qjs=Pjs×tgφ=0.33×1.02=0.337kvar
(17)交流电焊机
Kx=0.5,Cosφ=0.4,tgφ=2.291
Pjs=Kx×Pe=0.5×23.4=11.7kW
Qjs=Pjs×tgφ=11.7×2.291=26.805kvar
(18)交流电焊机
Kx=0.5,Cosφ=0.4,tgφ=2.291
Pjs=Kx×Pe=0.5×23.4=11.7kW
Qjs=Pjs×tgφ=11.7×2.291=26.805kvar
(19)高压汞灯
Kx=0.6,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.6×1=0.6kW
Qjs=Pjs×tgφ=0.6×1.02=0.612kvar
(20)高压汞灯
Kx=0.6,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.6×1=0.6kW
Qjs=Pjs×tgφ=0.6×1.02=0.612kvar
(21)平板式振动器
Kx=0.3,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.3×1.1=0.33kW
Qjs=Pjs×tgφ=0.33×1.02=0.337kvar
(22)插入式振动器
Kx=0.3,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.3×1.1=0.33kW
Qjs=Pjs×tgφ=0.33×1.02=0.337kvar
(23)钢筋切断机
Kx=0.65,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.65×5.5=3.575kW
Qjs=Pjs×tgφ=3.575×1.02=3.647kvar
(24)高压汞灯
Kx=0.6,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.6×1=0.6kW
Qjs=Pjs×tgφ=0.6×1.02=0.612kvar
(25)高压汞灯
Kx=0.6,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.6×1=0.6kW
Qjs=Pjs×tgφ=0.6×1.02=0.612kvar
(26)木工圆锯
Kx=0.65,Cosφ=0.6,tgφ=1.333
Pjs=Kx×Pe=0.65×5.5=3.575kW
Qjs=Pjs×tgφ=3.575×1.333=4.765kvar
(27)钢筋弯曲机
Kx=0.65,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.65×3=1.95kW
Qjs=Pjs×tgφ=1.95×1.02=1.989kvar
(28)钢筋调直机
Kx=0.65,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.65×4=2.6kW
Qjs=Pjs×tgφ=2.6×1.02=2.652kvar
(29)钢筋弯曲机
Kx=0.65,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.65×3=1.95kW
Qjs=Pjs×tgφ=1.95×1.02=1.989kvar
(30)灰浆搅拌机
Kx=0.5,Cosφ=0.55,tgφ=1.518
Pjs=Kx×Pe=0.5×3=1.5kW
Qjs=Pjs×tgφ=1.5×1.518=2.277kvar
(31)灰浆搅拌机
Kx=0.5,Cosφ=0.55,tgφ=1.518
Pjs=Kx×Pe=0.5×3=1.5kW
Qjs=Pjs×tgφ=1.5×1.518=2.277kvar
(32)蛙式夯土机
Kx=0.5,Cosφ=0.55,tgφ=1.518
Pjs=Kx×Pe=0.5×3=1.5kW
Qjs=Pjs×tgφ=1.5×1.518=2.277kvar
(33)高压汞灯
Kx=0.6,Cosφ=0.7,tgφ=1.02
Pjs=Kx×Pe=0.6×1=0.6kW
Qjs=Pjs×tgφ=0.6×1.02=0.612kvar
(34)总负荷计算
总的有功功率
Pjs=Kx×ΣPjs=0.9×256.28=230.652kW
总的无功功率
Qjs=Kx×ΣQjs=0.9×387.131=348.418kvar
总的视在功率
Sjs=(Pjs2+Qjs2)1/2=(230.6522+348.4182)1/2=417.846kVA
总电流计算
Ijs=Sjs/(1.732×Ue)=417.846/(1.732×0.38)=634.87A
3、干线进线截面及进线开关
在选择前应对照平面图和系统图先由用电设备至开关箱计算,再由开关箱至分配箱计算,选择导线及开关设备。
分配箱至开关箱,开关箱至用电设备的导线敷设采用铜橡皮绝缘导线空气明敷,室外架空铜导线按机械强度的最小截面为10mm2,由于这部分距离较短,因此不考虑电压降,只按安全载流量选择导线截面。
(1)1号干线上导线截面及分配箱、开关箱内电气设备选择
1)插入式振动器开关箱至插入式振动器导线截面及开关箱内电气设备选择(开关箱以下机械启动后需要系数取1):
a)计算电流
Kx=1,Cosφ=0.7
Ijs=Kx×Pe/(1.732×Ue×Cosφ)=1×1.1/(1.732×0.38×0.7)=2.388A
b)选择导线
选择BX-4×10,空气明敷时其安全载流量为85A,室外架空铜芯导线按机械强度的最小截面为10mm2,满足要求。
c)选择电气设备
选择开关箱内开关为DZ5-20/3,其脱扣器整定电流值为Ir=20A。
2)高压汞灯开关箱至高压汞灯导线截面及开关箱内电气设备选择(开关箱以下机械启动后需要系数取1):
a)计算电流
Kx=1,Cosφ=0.7
Ijs=Kx×Pe/(Ue×Cosφ)=1×1/(0.22×0.7)=6.494A
b)选择导线
选择BX-4×10,空气明敷时其安全载流量为85A,室外架空铜芯导线按机械强度的最小截面为10mm2,满足要求。
c)选择电气设备
选择开关箱内开关为DZ5-20/3,其脱扣器整定电流值为Ir=20A。
3)塔式起重机开关箱至塔式起重机导线截面及开关箱内电气设备选择(开关箱以下机械启动后需要系数取1):
a)计算电流
Kx=1,Cosφ=0.6
Ijs=Kx×Pe/(1.732×Ue×Cosφ)=1×55.5/(1.732×0.38×0.6)=140.543A
b)选择导线
选择BX-4×25,空气明敷时其安全载流量为145A,室外架空铜芯导线按机械强度的最小截面为10mm2,满足要求。
c)选择电气设备
选择开关箱内开关为DZ10-250/3,其脱扣器整定电流值为Ir=250A。
4)平板式振动器开关箱至平板式振动器导线截面及开关箱内电气设备选择(开关箱以下机械启动后需要系数取1):
a)计算电流
Kx=1,Cosφ=0.7
Ijs=Kx×Pe/(1.732×Ue×Cosφ)=1×1.1/(1.732×0.38×0.7)=2.388A
b)选择导线
选择BX-4×10,空气明敷时其安全载流量为85A,室外架空铜芯导线按机械强度的最小截面为10mm2,满足要求。
c)选择电气设备
选择开关箱内开关为DZ5-20/3,其脱扣器整定电流值为Ir=20A。
5)插入式振动器开关箱至插入式振动器导线截面及开关箱内电气设备选择(开关箱以下机械启动后需要系数取1):
a)计算电流
Kx=1,Cosφ=0.7
Ijs=Kx×Pe/(1.732×Ue×Cosφ)=1×1.1/(1.732×0.38×0.7)=2.388A
b)选择导线
选择BX-4×10,空气明敷时其安全载流量为85A,室外架空铜芯导线按机械强度的最小截面为10mm2,满足要求。
c)选择电气设备
选择开关箱内开关为DZ5-20/3,其脱扣器整定电流值为Ir=20A。
6)交流电焊机开关箱至交流电焊机导线截面及开关箱内电气设备选择(开关箱以下机械启动后需要系数取1):
a)计算电流
Kx=1,Cosφ=0.4
Ijs=Kx×Pe/(1.732×Ue×Cosφ)=1×23.4/(1.732×0.38×0.4)=88.884A
b)选择导线
选择BX-4×16,空气明敷时其安全载流量为110A,室外架空铜芯导线按机械强度的最小截面为10mm2,满足要求。
c)选择电气设备
选择开关箱内开关为DZ10-100/3,其脱扣器整定电流值为Ir=100A。
7)交流电焊机开关箱至交流电焊机导线截面及开关箱内电气设备选择(开关箱以下机械启动后需要系数取1):
a)计算电流
Kx=1,Cosφ=0.4
Ijs=Kx×Pe/(1.732×Ue×Cosφ)=1×23.4/(1.732×0.38×0.4)=88.884A
b)选择导线
选择BX-4×16,空气明敷时其安全载流量为110A,室外架空铜芯导线按机械强度的最小截面为10mm2,满足要求。
c)选择电气设备
选择开关箱内开关为DZ10-100/3,其脱扣器整定电流值为Ir=100A。
8)交流电焊机开关箱至交流电焊机导线截面及开关箱内电气设备选择(开关箱以下机械启动后需要系数取1):
a)计算电流
Kx=1,Cosφ=0.4
Ijs=Kx×Pe/(1.732×Ue×Cosφ)=1×23.4/(1.732×0.38×0.4)=88.884A
b)选择导线
选择BX-4×16,空气明敷时其安全载流量为110A,室外架空铜芯导线按机械强度的最小截面为10mm2,满足要求。
c)选择电气设备
选择开关箱内开关为DZ10-100/3,其脱扣器整定电流值为Ir=100A。
9)100m高扬程水泵开关箱至100m高扬程水泵导线截面及开关箱内电气设备选择(开关箱以下机械启动后需要系数取1):
a)计算电流
Kx=1,Cosφ=0.8
Ijs=Kx×Pe/(1.732×Ue×Cosφ)=1×20/(1.732×0.38×0.8)=37.985A
b)选择导线
选择BX-4×10,空气明敷时其安全载流量为85A,室外架空铜芯导线按机械
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 施工组织设计 16