FIDIC简明合同格式英文
CONTENTS
Agreement………………………………………………………………..…...4
Offer
Acceptance
Appendix
GeneralConditions
1GENERALPROVISIONS……………………………………………………..………….8
1.1Definitions
TheContract
Persons
Dates,TimesandPeriods
MoneyandPayments
OtherDefinitions
1.2Interpretation
1.3PriorityofDocuments
1.4Law
1.5Communications
1.6StatutoryObligations
2THEEMPLOYER……………………………………………………………………….10
2.1ProvisionofSite
2.2PermitsandLicences
2.3Employer’sInstructions
2.4Approvals
3EMPLOYER’SREPRESENTATIVES……………………………………………….11
3.1AuthorisedPerson
3.2Employer’sRepresentative
4THECONTRACTOR………………………………………………………………..…11
4.1GeneralObligations
4.2Contractor’sRepresentative
4.3Subcontracting
4.4PerformanceSecurity
5DESIGNBYCONTRACTOR…………………………………………………………..12
5.1Contractor’sDesign
5.2ResponsibilityforDesign
6EMPLOYER’SLIABILITIES…………………………………………………………...12
6.1Employer’sLiabilities
7TIMEFORCOMPLETION…………………………………………………………….13
7.1ExecutionoftheWorks
7.2Programme
7.3ExtensionofTime
7.4LateCompletion
8TAKING-OVER………………………………………………………………………….14
8.1Completion
8.2Taking-OverNotice
9REMEDYINGDEFECTS…………………………………………………………….…14
9.1RemedyingDefects
9.2UncoveringandTesting
10VARIATIONSANDCLAIMS…………………………………………………………..15
10.1RighttoVary
10.2ValuationofVariations
10.3EarlyWarning
10.4RighttoClaim
10.5VariationandClaimProcedure
11CONTRACTPRICEANDPAYMENT…………………………………………………16
ValuationoftheWorks
MonthlyStatements
InterimPayments
PaymentofFirstHalfofRetention
PaymentofSecondHalfofRetention
FinalPayment
Currency
DelayedPayment
12DEFAULT………………………………………………………………………….…….18
DefaultbyContractor
DefaultbyEmployer
Insolvency
PaymentuponTermination
13RISKANDRESPONSIBILITY……………………………………………….………19
Contractor’sCareoftheWorks
ForceMajeure
14INSURANCE………………………………………………………...…….….…….....20
14.1ExtentofCover
14.2Arrangements
14.3FailuretoInsure
15RESOLUTIONOFDISPUTES…….……………..…………………..……………...21
.
15.1Adjudication
15.2NoticeofDissatisfaction
15.3Arbitration
INDEXOFSUB-CLAUSES条款素引
ParticularConditions专用条款
RulesforAdjudication裁决条款
NotesforGuidance指南注释
Notes注释
Agreement
TheEmployeris________________________________________________of
______________________________________________________________
TheContractoris_______________________________________________of
______________________________________________________________
TheEmployerdesirestheexecutionofcertainWorksknownas_______________________________________________________________________
OFFER
TheContractorhasexaminedthedocumentslistedintheAppendixwhichformspartofthisAgreementandofferstoexecutetheWorksinconformitywiththeContractforthesumof_________________________________________________________(inwords)
__________________________________(infigures)(___________________________)
orsuchothersumasmaybeascertainedundertheContract.
Thisoffer,ofwhichtheContractorhassubmittedtwosignedoriginals,maybeacceptedbytheEmployerbysigningandreturningoneoriginalofthisdocumenttotheContractorbefore_____________________________________________________________(date)
TheContractorunderstandsthattheEmployerisnotboundtoacceptthelowestoranyofferreceivedfortheWorks.
Signature:
___________________________Date:
__________________________
Name:
______________________________Authorisedtosignonbehalfof(organization
Name):
___________________________
Capacity:
_____________________________________________________________
ACCEPTANCE
TheEmployerhasbysigningbelow,acceptedtheContractor’sofferandagreethatinconsiderationfortheexecutionoftheContract.ThisAgreementcomesintoeffectonthedatewhentheContractorreceivesoneoriginalofthisdocumentsignedbytheEmployer.
Signature:
___________________________Date:
__________________________
Name:
______________________________Authorisedtosignonbehalfof(organization
Name):
___________________________
Capacity:
_____________________________________________________________
APPENDIX
ThisAppendixformspartoftheAgreement.
[Note:
withtheexceptionoftheitemsforwhichtheEmployer’srequirementshavebeeninserted,theContractorshallcompletethefollowinginformationbeforesubmittinghisoffer.]
ItemSub-ClauseData
DocumentsformingtheContract
listedintheorderofpriority…1.1.1
Document(deleteifnotapplicable)DocumentIdentification
(a)TheAgreement………………_____________________________
(b)ParticularConditions………._____________________________
(c)GeneralConditions…………_____________________________
(d)TheSpecification……………_____________________________
(e)TheDrawings……………….._____________________________
(f)TheContractor’stendered
design_____________________________
(g)Thebillofquantities…………______________________________
(h)…………………………………______________________________
(i)…………………………………______________________________
TimeforCompletion…………………1.1.9……__________________________days
LawoftheContract………………….1.4………LawoftheCountry﹡_____________
_____________________________
Language……………………………..1.5………_____________________________
ProvisionofSite………………………2.1……...OntheCommencementDate﹡_____
_____________________________
Authorisedperson…………………….3.1……..._____________________________
NameandaddressofEmployer’s
Representative(ifknown)…………….3.2………______________________________
_____________________________
Performancesecurity(ifany):
Amount………………………………4.4………______________________________
Form…………………………………4.4………_______________________(details)
﹡Employertoamendasappropriate
ItemSub-ClauseData
RequirementsforContractor’s
Design(ifany)……………………5.1………..SpecificationClausesNo’s________
____________________________
Programme:
Timeforsubmission……………7.2…………Within14days﹡oftheCommencement
Date.
Formofprogramme……………7.2…………_______________________________
_______________________________
Amountpayableduetofailureto
complete…………………………7.4………….______________________perdayup
toamaximumof10%﹡ofsumstatedintheAgreement
Periodfornotifyingdefects……9.1&11.5365days﹡calculatedformthedatestatedinthenoticeunderSub-Clause8.2
Variationprocedure
Dayworkrates………………10.2………._______________________________
_______________________________
_________________________(details)
ValuationoftheWorks﹡
LumpsumPrice……………11.1………..._________________________(details)
Lumpsumpricewithschedules
ofrates………………………11.1…………________________________(details)
Lumpsumpricewithbillof
quantities…………………...11.1………….________________________(details)
Remeasurementwithtender
billofquantities…………….11.1………….________________________(details)
Costreimbursable…………11.1………….________________________(details)
PercentageofvalueofMaterials
andPlant………………………..11.2………….Materials__________________80%﹡
Plant____________________90%﹡
﹡Employertoamendasappropriate
ItemSub-ClauseData
Percentageofretention…………11.3………___________________________50%
Currencyofpayment……………11.7………______________________________
Rateofinterest………………..…11.8………____________________%perannum
Insurances……………………….14.1
_______________________________________________________________________
Typeofcover﹡Amountofcover﹡Exclusions﹡
___________________________________________________________________
TheWorks,Materials,PlantThesumstatedinthe
andfeesAgreementplus15%________________________
Contractor’sEquipmentFullreplacementcost________________________
ThirdPartyinjurytopersons
anddamagetoproperty__________________________________________
Workers_________________________________________
Othercover﹡______________________________________________
_______________________________________________________________________________
Arbitration
Rule…………………………15.3…………UNCITRALArbitrationRules﹡
____________________(details)
Appointingauthority………15.3…………PresidentofFIDICorhisnominee﹡
_______________________(details)
PlaceofArbitration……….15.3…………TheCountry﹡__________________
﹡Employertoamendasappropriate
GeneralConditions
GeneralProvisions
1.1
DefinitionsIntheContractasdefinedbelow,thewordsandexpressions
definedshallhavethefollowingmeaningsassignedtothem,exceptwherethecontextrequiresotherwise:
TheContract1.1.1“Contract”meanstheAgreementandtheotherdocumentslistedintheAppendix.
1.1.2“Specification”meansthedocumentaslistedintheAppendix,includingEmployer’srequirementsinrespectofdesigntobecarriedoutbytheContractor,ifany,andanyVariationtosuchdocument.
1.1.3“Drawing”meanstheEmployer’sdrawingsoftheWorksaslistedintheAppendix,andanyVariationtosuchdrawings.
Persons1.1.4“Employer”meansthepersonnamedintheAgreementandthelegalsuccessorsintitletothisperson,butnot(exceptwiththeconsentoftheContractor)anyassignee.
1.1.5“Contractor”meansthepersonnamedintheAgreementandthelegalsuccessorsintitletothisperson,butnot(exceptwiththeconsentoftheEmployer)anyassignee.
1.1.6“Party”meanseithertheEmployerortheContractor.
Dates,Timesand1.1.7“CommencementDate”meansthedate14daysafter
PeriodsthedatetheAgreementcomesintoeffectoranyother
dateagreedbetweentheParties.
1.1.8“day”meansacalendarday.
1.1.9“TimeforCompletion”meansthetimeforcompleting
theWorksasstatedintheAppendix(orasextendedunderSub-Clause7.3),
- 配套讲稿: