高速公路收费系统监控系统施工组织设计
高速公路收费系统监控系统施工组织设计
机电工程监控、收费、通信系统供货与安装 施工组织设计
高速公路收费系统
监控系统施工组织设计
第1页
机电工程监控、收费、通信系统供货与安装 施工组织设计
目录
1
编制依据和编制原则···········································································6 2
编制依据·····················································································6编制原则·····················································································6工作原则和指导思想······································································6施工组织目标···············································································7
投标人省内优势·················································································8
公司的优势··················································································8熟悉某省项目环境·········································································8良好的市场信誉············································································8优质的施工质量············································································9及时的售后服务············································································9
3工程概述··························································································10
工程概况····················································································10工程范围····················································································10
4施工组织机构设置·············································································12
施工组织机构及人员配备·······························································12技术力量和劳动力计划··································································18
5施工进度计划···················································································19
工期目标····················································································19工程施工进度计划表······················································19施工进度保证的组织机构·······························································19施工进度计划的控制·····································································20
第2页
机电工程监控、收费、通信系统供货与安装 施工组织设计
6项目实施的总体规划··········································································23
工程设计和软件开发·····································································23设计文件的审批和检查··································································24工厂监造与工厂测试·····································································25临时工程与设施的解决方案····························································26施工调查····················································································29与相关单位的协调········································································30现场开工准备··············································································30物资管理····················································································31不合格品控制··············································································35竣工文件和档案资料··································································36
7总体施工方案···················································································37
施工基本要求··············································································37施工阶段划分··············································································37人员和机械组织···········································································38总体施工方法··············································································39
8主要工程项目的施工方案及施工工艺·····················································40
施工流程及一般施工顺序·······························································40收费系统设备··············································································41监控系统设备··············································································49通信系统设备··············································································64电源系统····················································································74接地系统····················································································77软件安装及系统调试方案·······························································78
第3页
机电工程监控、收费、通信系统供货与安装 施工组织设计
9
系统联调方案··············································································82
施工管理··························································································86
做好施工准备··············································································86技术管理保证措施········································································86加强组织管理··············································································87加强人员管理··············································································88做好物资供应工作········································································88加强机械管理··············································································89工期控制措施··············································································89做好同相关承包人的施工协调工作···················································90应对施工工期安排中意外情况的措施················································90工期保证体系及框图··································································91
10施工质量保证措施···········································································92
质量目标··················································································92质量保证原则············································································92质量管理机构············································································93质量保证体系框图······································································93质量保证岗位职责······································································95工程质量的控制·········································································99各项质量保证措施····································································108
11
施工安全保证措施·········································································113
安全目标················································································113安全保证原则··········································································113安全管理机构图·······································································113
第4页
机电工程监控、收费、通信系统供货与安装 施工组织设计
12
安全保证体系框图····································································114安全保证岗位职责····································································115安全生产措施··········································································117
文明施工保证措施·········································································123
文明施工组织机构····································································123文明施工保证措施····································································123创建文明标准工地措施·····························································126
13
施工环保措施···············································································126
卫生措施················································································126防止大气污染措施····································································127防止水污染措施·······································································127防止施工噪声污染措施·····························································127
14
售后服务承诺···············································································128
服务宗旨················································································128售后服务承诺··········································································128售后服务保障措施····································································128
15
创优规划·····················································································131
创优组织机构··········································································131创优措施················································································131
16
附录一、工程进度计划表································································135
第5页
机电工程监控、收费、通信系统供货与安装 施工组织设计
1编制依据和编制原则
编制依据
1)《***********电工程监控、收费、通信系统供货与安装招标文件》、《招标文
件澄清及补遗书》;
2)国家及有关部委现行有关施工规范、技术标准和验收标准;3)本投标人类似工程施工经验;
编制原则
1)以科学的管理提供质量保证,以完善的质量保证措施和体系,确保工程质量
优良。
以完善的安全保证措施和管理体系,确保施工安全和人身安全。
2)确保工期目标实现,确保根据招标文件要求的完工时间和全线通车运行日期
完成工程安装调试。
3)优化资源配置,快捷高效的干好本工程,实现社会效益和社会经济效益双丰
收。
4)推广使用新技术、新工艺、新材料,搞好技术创新,促进管理创新,提高工
程质量,降低工程成本。
5)加强环境保护和文明施工管理,团结协作,促进施工生产。
6)以作业队为施工实体,项目部内资源合理配置,既能集中力量进行主要项目
施工,又能灵活机动分项、分段施工。
7)积极与业主、设计、监理、相关施工单位、某省省政府相关部门联系,搞好
施工协调配合。
8)坚持“用户至上”和提供优质服务的指导思想,认真履行合同,并做到“合同执
行完,服务不终止”。
9)遵纪守法,积极配合,促进廉政建设。
遵守业主关于廉政建设的有关规定。
工作原则和指导思想
工作原则:
尊重业主,服从监理,配合设计及其他承包商,信守合同;详细调
第6页
机电工程监控、收费、通信系统供货与安装 施工组织设计
查,优化方案,搞好协调,确保进度。
指导思想:
主动协调创条件,文明施工抓安全,科学管理保进度,严字当头创全优。
施工组织目标
工期目标:
若我方被确定为本机电工程的承包人,在接到中标通知书后,立即展开施工动员,并根据招标文件的预计通车时间确定该工程的完工日期,确保全线如期正常运营。
运行验收后12个月的缺陷责任期内提供优质的售后服务。
质量目标:
优质工程
以招标文件、设计文件及国家颁发的相关技术规范和验收标准为准则,制定创优规划,实现全线工程创优。
实现无大工程质量事故,无技术责任事故,无工程质量隐患事故,工程一次验收合格率100%,优良率96%以上。
经济目标:
为业主获得最大投入产出比,采用新技术新工艺、合理安排、精心组织,在不降低设备档次、不降低施工质量、不延长工期的情况下最大限度降低施工成本,实现双赢。
安全目标:
安全目标为:
实现无重大人身伤亡事故,无重大机械事故,无重大交通事故,消灭重大责任死亡事故;确保施工安全,确保交通安全。
文明施工目标:
科学管理、生产有序、团结协作、多方配合、保护环境及原有设施、场地整洁,争创文明施工工地。
环保目标:
保持施工现场、施工临时基地环境清洁,减少噪声、振动、废气和固体废弃物对环境的影响,符合国家和某省省有关环境保护法规及条例的要求。
第7页
机电工程监控、收费、通信系统供货与安装 施工组织设计
2投标人省内优势
公司的优势熟悉某省项目环境
本投标人在本项目投标中的的技术优势:
本投标人参与了某省省全省收费系统网路的规划和配置,并开发了全省统一收费软件,对某省省高速公路收费系统有较深入的了解。
在某省省高速公路各路段收费系统开通中,都是以本投标人为主进行联网及开通调试,保证了各路段按时开通并进行运营收费。
本投标人是某省省高速公路机电省中心系统建设的承包人,对各路段与省中心的联网有着深刻的理解并熟悉联网的方案、协议和规范,不需要其他承包商的协助和配合,能够独立完成与省中心的联网工作。
本投标人对某省省高速公路三大系统的管理模式、设备配置、系统组成及系统扩充有深入的了解,能确保机场二期高速公路与其他路段通信系统、收费系统和监控系统的相接。
本投标人承诺在本项目实施中将提供投标人多年来在某省省高速公路机电领域总结的设计、施工和运行的宝贵经验,为机场二期高速公路机电系统工程提供先进的、合理的、稳定的方案和建议,把机场二期高速公路机电系统建成